Cagni Park North Athletic Complex - Phase 1

Visit cagniparkproject.com

Project Limits

135 Street to 137 Street from Northeast 8 Avenue to Northeast 9 Avenue

Scope of Work

  • Design, permit and construction of the complex amenities
  • Amenities will include:
    • Aquatic facility
    • Multipurpose field
    • Playground
    • Parking

Project Timeline

  • Design - Now through August 2022
  • Construction - September 2022 through October 2023

Project Team

Jeff Geimer
City of North Miami Capital Project Manager
Email Jeff Geimer

Sam Brinson
City of North Miami Parks and Recreation Director
Email Sam Brinson

Consultant

  Bermello Ajamil & Partners 

Contractor

 Thornton Construction

Overview Video of Schematic Design

Slideshow Presentation of Schematic Design - Concept Plans

Cagni Park BA Schematic Design

Project Photos

Cagni Park Design Development Plan Opens in new window