Water Main Design Improvements - 2019 Phase 2

Project Limits

Project Fact Sheet (PDF)

  • Phase A
    • Northeast 6 Avenue from 131 Street to 137 Street 
    • 137 Street from Northeast 6 Avenue to Northeast 7 Avenue 
  • Phase B 
    • 118 Street from Biscayne Canal Road to West Dixie Highway to 118 Terrace 
    • West Biscayne Canal Road from 116 Street to 118 Terrace 
  • Phase C
    • Northwest 8 Avenue from 140 Terrace to 142 Street
    • 140 Terrace from Northwest 7 Avenue to Northwest 8 Avenue
    • Northwest 7 Avenue from 137 Street to 141 Street
    • 141 Terrace from Northwest 7 Avenue to Northwest 8 Avenue

Scope of Work

  • Design 2,700 linear feet of 12” water main
  • Design 7,600 linear feet of 8” water main
  • Install 2,700 linear feet of 12” water main
  • Install 7,600 linear feet of 8” water main

Project Timeline

  • Design - Complete
  • Construction
    • Phase A – Complete 
    • Phase B – Now through December 2023 
    • Phase C – April 2023 through December 2023

Project Team

Chuks Okereke
City of North Miami - City Engineer
Email Chuks Okereke

Yadly St.Fort
City of North Miami - City Engineer
Email Yadly St. Fort

Consultant

Kimley-Horn

Contractor

  • Phase A - Acosta Tractors 
  • Phase B – To Be Determined 
  • Phase C – Bazile USA