Pump Station A Rehabilitation

Project Limits

125 Street and Northwest 11 Avenue

Scope of Work

  • Prepare construction documents
  • Rehabilitate the facility

Project Timeline

  • Design - Completed May 2020
  • Permitting - Completed January 2021
  • Construction - October 2021 through September 2022

Project Team

Chuks Okereke
City of North Miami City Engineer
Email Chuks Okereke

Consultant

AECOM

Contractor

To Be Determined