Arch Creek North Drainage Improvements

Project Limits

130 Street to 133 Street from Northeast 12 Avenue to Northeast 14 Avenue

Scope of Work

  • Install 2,500 linear feet of French drain
  • Install 32 catch basins
  • Install 500 linear feet of high-density polyethylene (HDPE) pipe
  • Install 16 manholes with skimmers

Project Timeline

Completed September 2020

Project Team

John Quintero
City of North Miami - City Engineer
Email John Quintero

Consultant

King Engineering

Contractor

Top Craft

Arch Creek North - Progress Photo