SCOPE OF WORKFurnishing and installing the below mentioned length of 8-inch, 10-inch and 12-inch ductile iron pipe sanitary sewer force main and fittings in the site of work defined in the Construction Documents. The work for this project consists of 250 linear feet of 8-inch ductile iron pipe and fittings, 8,390 linear feet of 10-inch ductile iron pipe and fittings, and 1,600 linear feet of 12-inch ductile iron pipe and fittings. DEADLINE FOR ADDITIONAL INFORMATION & CLARIFICATIONFriday, October 15, 2021, by no later than 3:30 PM (EST) DEADLINE FOR SUBMITTAL OF BIDSFriday, December 3, 2021, by no later than 3:30 PM (EST)
Friday, December 10, 2021, by no later than 3:30 PM (EST)*Deadline was extended via Addendum 4*
NON-MANDATORY PRE-BID CONFERENCEWednesday, October 6, 2021, @ 10:00 AMPepper Park1400 NW 135th Street North Miami, FL 33167
|