Capital Improvement Projects
PROJECTS
Neighborhood Improvements
Public Spaces
Infrastructure
North Miami CRA Projects
Municipal Partners – Roadway Construction
Completed Projects201620172018
Completed Projects - 2016
Project Limits126 Street to 134 Street and Griffing Boulevard to NE 12 Avenue
Scope of Work • Identify planting locations • Gain the approvals necessary to install trees • Complete installation of 117 trees
Project TimelineComplete
Project TeamCity of North Miami Sustainability AdministratorKent Walia
ContractorCountry Bill’s Lawn Maintenance, Inc.
Project Limits123 Street and North Bayshore Drive123 Street and Sans Souci BoulevardBiscayne Boulevard and Sans Souci Boulevard
Scope of Work • Restore the walls gateway features are installed on • Upgrade gateway feature signage • Relandscape surrounding areas
Project TeamCity of North Miami Capital Project ManagerJeff Geimer
Project LimitsCitywide
Scope of Work • Perform a study to determine where speed limits can be reduced • Gain approval for speed reduction from the County • Install new 25 MPH signs (120 signs)
Project TeamCity of North Miami Transportation PlannerJohn O’Brien
ConsultantKimley-Horn
ContractorCoreland Construction Corp.
Scope of Work • Prioritize roadway resurfacing work based on existing study • Complete work in each of the Council Districts
Project TimelineCompleate
Project TeamCity of North Miami Streets and Stormwater Superintendent Rick Cade
ContractorMetro Express Inc.
Scope of Work • Prioritize sidewalk repair work based on existing requests • Complete work in each of the Council Districts
Project TeamCity of North Miami Streets and Stormwater SuperintendentRick Cade
Contractor Coreland Construction Corp.
Project LimitsNorth Bayshore Park – 12220 North Bayshore Drive
Scope of Work • Design and permit the boardwalk • Remove invasive vegetation and trim back native material • Reconstruct the boardwalk
Project TeamCity of North Miami Parks, Recreation and Cultural Arts DirectorDerrick Corker
ContractorPac Comm, Inc.
Scope of Work • Relocate the dog park within the facility • Replace the deteriorated fence with a six-foot decorative fence
ContractorAlex Fencing
ContractorWilliams Welding
Project LimitsNE 12 Avenue from 125 Street to 135 Street
Scope of Work • Identify planting locations • Gain the approvals necessary to install trees • Complete installation of 35 trees
ContractorBannerman Landscaping
Project LimitsSans Souci Tennis Center – 1795 Sans Souci Boulevard
Scope of Work • Patch, seal and resurface 12 tennis courts • Replace deteriorated nets
ContractorFast-Dry Courts
Project LimitsThomas Sasso Pool – 12502 NW 11 Avenue
Scope of Work • Replace deteriorated roof • Upgrade pump house equipment • Resurface pool deck • Replace deteriorated pool furnishings
City of North Miami Capital Project ManagerJeff Geimer
Photos before improvements
Photos after improvements
Project LimitsNorth Miami City Hall – 776 NE 125 Street
Scope of Work • Pressure clean the building’s exterior • Upgrade restroom facilities on the third floor • Upgrade restroom facilities on the fourth floor
Project TeamCity of North Miami Public Works Operations ChiefTom Positano
ContractorMiami Shores Plumbing
Project LimitsDistrict 1 and District 3
ContractorsH&R PavingMetro Paving
Project LimitsEast of NE 6 Avenue from 144 Street to 145 Street
Scope of Work • Install an irrigation system • Relandscape area • Improve walkway
Scope of Work • Brush, scrub and acidize the eight water supply wells • Inspect and upgrade the motors and pumps as necessary
Project TeamCity of North Miami Water Plant SuperintendentPavel Vida
ContractorAC Schultes
Project LimitsSans Souci Gated Community
Scope of Work • Remove the four existing chain link closures • Install three, six-foot tall Trex fence closures • Install one, six-foot tall concrete block closure • Install one, six-foot tall concrete block closure • Install landscaping
Project TimelineNow through February 2017
ContractorSolutions Capital Group, Inc.